June 18, 2011
  • The location of the proposed AERIE condominium development.
The location of the proposed AERIE condominium development. (Amy Senk, Daily…)

The AERIE condominium development may have cleared the Coastal Commission and City Council after nearly three years of hearings and debate.

But construction of the seven-unit building along Ocean Boulevard and Carnation Avenue won't begin until the end of the year at the earliest, owner Richard Julian said in an interview.

"We have to do working drawings," Julian said. "The final drawings are very detailed, very expensive and take four to five months."

Julian said demolition could begin before the end of the year, but he and his family members stay in the apartments currently on the site, so they want to wait until everything is set before they begin.

"We have to see how that goes," he said. "There will be a lot of little things that have to be done."

Advertisement

The Coastal Commission on Wednesday unanimously approved AERIE's plans after rejecting the project in April 2010, and having the plans withdrawn in March just moments before another no vote seemed imminent.

Since April 2010, the project was reduced in size by one unit with a 17% reduction in square feet and a 61% reduction in bluff excavation. Construction time was cut from 32 to 25 months.

Opponents said the project, at 51,124 square feet, was still too big for the neighborhood, and a few commissioners on Wednesday said they too had concerns. But in the end, the commissioners agreed with the staff recommendation of approval.

After the hearing in Marina del Rey, Julian and several supporters drove to Corona del Mar to the AERIE project site and had a party.

"Every time I turned around, there was somebody new there," he said. "Everybody was really excited. We had a lot of Champagne."

CdM quad drenched in senior prank

Corona del Mar High School seniors staged a water balloon fight this week as part of a senior prank that lasted about 10 minutes and drenched the campus quad.

Some students said they had warning before the prank and were able to run into classroom buildings to avoid being pelted by water balloons and water guns.

Several students posted photos and videos on YouTube and Facebook — including one wearing a gorilla mask — running around the quad before heading off to the swimming pool.

Seniors also placed lunch tables on the school roof and dumped sand in the quad. Earlier this month, some students said that seniors let crickets loose in the school.

Daily Pilot Articles Daily Pilot Articles
|
|
|